The DuPage River Salt Creek Workgroup, DRSCW, formed in 2005 in response to concerns about Total Maximum Daily Loads, TMDLs, developed for the east and west branches of the DuPage River and Salt Creek located in portions of Cook, DuPage, and Will counties in northeastern Illinois. The DRSCW seeks to implement targeted watershed activities that resolve priority waterway problems cost-effectively.
In 2015 and 2020, a Special Condition to DRSCW NPDES permits was added that substantially increased financial commitments to restoration efforts focused on improving aquatic life. The Special Condition includes 10 stream restoration projects, two studies, and the development of a Nutrient Implementation Plan.
For more information, see drscw.org
Physical Projects
Spring Brook Phase 2
In 2025, Year 5 of a planned five-year post-project monitoring was conducted at the Phase 2, Stream Restoration Project at the Blackwell Forest Preserve in Wheaton, DuPage County. This stream restoration project included the removal of the Arrow Road dam. The channel was realigned into the adjacent floodplain in order to increase sinuosity and mimic natural geomorphology, and to create22.8 acres of wetlands. After five years of post-project monitoring, Spring Brook Phase 2 has met its post-project targets for habitat, Qualitative Habitat Evaluation Index, QHEI, and Fish Index of Biotic Integrity, fIBI, both within the project footprint and at sites monitored as part of the post-project impact evaluation. Post- project Macroinvertebrate Biotic Index, MIBI, targets have not been met but it is expected that mIBI scores will continue to increase at the site as the restoration matures.
Klein Creek Streambank Stabilization Project
The DuPage River Salt Creek Workgroup entered a Memorandum of Understanding with the Village of Carol Stream to fund the river resource improvement elements of the Klein Creek Section I Stream Bank Stabilization Project, which was completed in 2022. This project re-meandered a section of the channel and increased its length by approximately 200 feet. As the longitudinal slope was too flat for riffle structures, two rock substrate areas were added to provide riffle-type benefits. Streambanks were stabilized with vegetated rock toes or with rootwads embedded at outside bends, as well as with rock vanes, or stream barbs, at strategic locations. The top of the streambank was lowered adjacent to approximately 1.4 acres of newly created wetlands.
Activities in 2025 at the Klein Creek Section I Stream Bank Stabilization Project focused on vegetation maintenance and monitoring, M&M, activities and on post-project monitoring. The naturalized areas included in the M&M activities include 16.76 acres of upland prairie/economy prairie, 3.74 acres of open riparian area, 1.44 acres of sedge meadow, and 0.93 acres of shallow emergent area. Based on the results of the 2025 vegetation monitoring, the Klein Creek Streambank Stabilization - Section I project has exceeded expectations for its third year of restoration. Planted species and native species from the seed soil bank are highly abundant and will continue to increase coverage in future years. The In-Stream Structures, Upland Restoration Zones, and Wetland Restoration Zones have all met the designated third year performance standards for 2025.
The second year of biological and habitat 5-year post-project monitoring at the site took place in 2025. Post-project mIBI, fIBI, and QHEI have all improved since the pre-project monitoring and are expected to continue to increase as the restoration matures.
Fullersburg Woods Dam Removal and Stream Restoration
In November of 2023, the DuPage River Salt Creek Workgroup in cooperation with the Forest Preserve District of DuPage County, FPDDC, began construction on the Fullersburg Woods Dam Removal and Stream Restoration Project in the Fullersburg Woods Forest Preserve, Village of Oak Brook, DuPage County, Illinois. The Project was designed and permitted with assistance from Water Quality Hey and Associates, constructed by V3 Companies with construction management services provided by the Metropolitan Water Reclamation District of Greater Chicago, MWRDGC. The project objectives were to establish fish passage on Salt Creek by the removal of the Graue Mill Dam, to improve dissolved oxygen, and to raise QHEI, fIBI and mIBI scores in Salt Creek.
Construction of the project was completed between November 2023 and December 2024. Construction included stream restoration practices such as the removal of the Graue Mill dam, the installation of nine rock riffles, the digging of two pools, and the placement of 1,000 linear feet of stream bank restoration. In addition to the stream restoration practices, all of the amenities included in the Master Plan for Salt Creek at Fullersburg Woods were also installed in the summer and fall of 2024. Amenities near the Graue Mill included an ADA-accessible trail, a river overlook, a landscape feature on the opposing bank, a re-designed mill raceway with water source and cascade, and a motor to turn the waterwheel. Work conducted by the Fullersburg Woods Nature Center included rehabilitation and waterproofing of the existing, but failing, floodwall.
Activities in 2025 at the Fullersburg Woods Dam Removal and Stream Restoration Project focused on vegetation maintenance and monitoring activities and post-project monitoring. Two of four vegetation performance standards applicable for 2025 (Year 1) have been met. The Upland Enhancement community had sparser cover due to higher than expected canopy cover and invasive garlic mustard (Alliaria petiolata) as a dominant species, which will continue to be addressed in 2026 using a more shade tolerant supplemental seed mix and continued weed control efforts. It should be noted, however, that an additional three performance standards not yet applicable were also met in 2025. These standards included being Native Mean Coefficient of Conservatism, value of 3.5 or greater and Native Floristic Quality Index of 20 or greater. Future management during 2026 include, a prescribed burn in early winter/early spring if conditions allow it, a supplemental seeding, continued weed control, 6-8-inch-high mowing, and installations of native plants, trees and shrubs. With these continued efforts, each native vegetation community within Fullersburg Woods is anticipated to become further established.
The project’s objectives were to raise QHEI above its pre-project average of 47.45, raise fIBI at the sites upstream of the dam above its pre-project average score of 14.0, raise mIBI above its pre-project average score of 25.5 for approximately 1.25 river miles of Salt Creek. Within one year of the completion of the project’s construction, the QHEI objective, 2025 QHEI score of 77-90.5, and the fIBI objective, 2025 fIBI scores of 26-33, were met at all sites within the project footprint. The mIBI objectives, scores of 34.3-43.2, were met at three of the four sites. It is expected that the mIBI at site SC56C will continue to improve as vegetation is established and will meet the objectives in future years of post-project sampling. It is important to note that all QHEI scores within the Project footprint are now classified as “good” and one site, SC56B, has a macroinvertebrate score of 43.2 meeting the Illinois General Use Attainment standard.
In addition to raising fIBI scores, the project has an objective to increase fish passage to the 20 miles of the Salt Creek mainstem and its tributaries located upstream of the removed Fullersburg Woods (Graue Mill) dam. Comparison of pre-project monitoring data identified 16 species of native fish that were historically blocked by the dam. Post-project assessments in 2025 identified eight species that have moved into Salt Creek above the former dam location. These species include the blackside darter, logperch, smallmouth bass, rosyface shiner, central stoneroller, emerald shiner, northern pike, and the horney head chub. It should also be noted that the other eight species previously confined below the dam were not identified anywhere in the Salt Creek watershed in 2025.
Lower East Branch Stream Restoration Project
In 2025, the DuPage River Salt Creek Workgroup signed an updated contract with inter-fluve to complete the final design, permitting, and preparation of the bid documents for reaches 2-4 of the Lower East Branch Stream Enhancement Project. Work completed includes the development of 1D and 2D hydraulic modes for the project area and preliminary work on the 75% design plans. It is expected that the final design plans, bid documents, and all required permits will be completed by March 2027.
Nutrient Implementation Plan
In December 2023, the DuPage River Salt Creek Workgroup in cooperation with the Lower DuPage River Watershed Coalition, LDRWC, submitted the Nutrient Implementation Plan, NIP, for the East Branch DuPage River, West Branch DuPage River, Lower DuPage River, and Salt Creek of the Illinois River to the Illinois EPA. A crucial step in developing this NIP was establishing a watershed threshold concentration for total phosphorus, TP, that is protective of aquatic life in the NIP area. A relationship between TP concentrations, fish species, and macroinvertebrate taxa and their indices of biotic integrity was established using a multivariate analysis published in 2023 by the watershed groups. The analysis, which drew on paired biological, chemical, and physical data from 640 sites in northeast Illinois, found fish species and the Fish Index of Biotic Integrity, fIBI, were more sensitive to TP concentration variation than the macroinvertebrate taxa and the Macroinvertebrate Index of Biotic Integrity. The 75th percentile of sites in the fIBI range of 41 and 49, meeting and exceeding the General Use standard for aquatic life, was found to correspond to an upper TP threshold concentration of 0.277 milligrams per liter (mg/L). The NIP adopted this as the upper threshold of the watershed TP target.
Analysis of the mean TP concentrations at sites monitored by the watershed groups’ rolling bioassessments under various flow regimes show a clear differentiation between sites. Annual mean concentrations at sites downstream of wastewater treatment plants, a product of both wastewater and non-wastewater (stormwater and background sources, summarized as urban), ranged from 0.70 mg/L to 2.12 mg/L; concentrations at urban-only sites (upstream of any wastewater treatment plant influence) had total phosphorus concentrations ranging nearly an order of magnitude lower, 0.03–0.53 mg/L. Instream flow was an important factor, with TP concentrations falling at both wastewater-influenced and urban sites as flow increased. Mean annual concentrations at all urban sites were beneath the watershed threshold (0.277 mg/L) in all years sampled when flows were above the 25th percentile. Sites downstream of wastewater treatment plant outfalls had a TP concentration significantly above the watershed threshold in all years. Aggregation of the flows and water quality data to allow for reduction scenarios modeling showed that while wastewater treatment plants contributed 13% to 28% of annual flow, they contributed more than 80% of annual ambient instream TP.
Modeling was conducted using the QUAL2Kw platform to identify potential management scenarios that would decrease ambient instream TP concentrations below the identified TP watershed threshold. Receiving water models were developed for each basin and included the connectivity of the East and West Branches of the DuPage River model outputs to inform the headwater conditions of the Lower DuPage River. Notably, the headwater condition includes the assumption, as recommended by the NIP, that all upstream wastewater treatment plants will be operating with a 0.35 mg/L TP limit. Following model calibration efforts, channel geometry and hydraulics were modified for the Lower DuPage River and Salt Creek to reflect the imminent removals of dams on these waterways; both dams have since been removed. Ultimately, the suite of scenarios modeled demonstrated that an effluent permit limit of 0.35 mg/L (for an effective effluent concentration of 0.28 mg/L) for wastewater treatment plants along Salt Creek and the West and East Branches of the DuPage River would be sufficient to achieve the watershed threshold value satisfactorily.
The modeled reductions of effluent TP concentrations did not show meaningful improvements in predicted minimum and mean dissolved oxygen concentrations due in part to localized persistence of low gradients or flow restrictions which also factor into existing dissolved oxygen impairments.
The NIP recommended targeted physical projects focused on eliminating dissolved oxygen sags and improving instream habitat be implemented. Recommendations include that wastewater treatment plants discharging to Salt Creek and the East and West Branches of the DuPage River adopt an effluent limit of 0.35 mg/L TP (leading to an effective mean effluent concentration of 0.28 mg/L, assuming a 20% margin of safety) seasonal geometric mean for warm weather months (May-October) as part of an annual 0.50 mg/L TP geometric mean.
Throughout 2025, the DRSCW coordinated with the Illinois EPA and environmental advocacy groups to develop language to include the NIP recommendation in future wastewater treatment plant NPDES permits. It is expected that NPDES permits including the NIP recommendation will be issued in 2026.