The Fox River Study Group, FRSG, is a diverse coalition of stakeholders who have been working since 2003 to improve the health of the Fox River for the benefit of the nearly 1 million people in the Fox River Valley and for over 300,000 people whose drinking water comes from the river. The study group is using research, data, and collaboration to guide the region toward a cleaner, safer, and more beautiful Fox River and to support sustainable policies and development across the Fox River watershed. The group’s study area encompasses 1,405 square miles of the Fox River watershed from the Stratton Dam in McHenry County to the mouth of the river in LaSalle County. The watershed includes an additional 1,253 square miles upstream in the Chain O’Lakes region in Illinois and into Wisconsin to the river’s source near Waukesha.
Since completing a 2022 update of their 2015 Fox River Implementation Plan, FRIP, the group has been working on plan implementation. The group worked with the U.S. Army Corps of Engineers on a feasibility study that looked at the benefits of removing dams on the river. FRSG has collected water quality data in the watershed for 23 years. The group also continues to contract work with the U.S. Geological Survey, Illinois State Water Survey, and the Illinois Natural History Survey to collect and analyze data on water quality and aquatic life in the Fox River watershed. The FRSG conducted a number of public outreach events during 2025 in addition to virtual monthly board meetings that are open to all.
Implementation of the 2022 Fox River Implementation Plan
The 2022 FRIP calls for the achievement of a 0.5 mg/L total phosphorus limit on effluent from major wastewater treatment plants by 2030.
The chart shows the reductions wastewater treatment plants have achieved. A compilation of the 2025 data is expected to be obtainable from the Illinois EPA around mid-year 2026.
- Supporting of removal of dams along the Fox mainstem as identified in the Corps study and taking the lead in monitoring the water quality impacts of removed dams
- Encouragement of state-of-the-art watershed management practices that can mitigate the impact of projected population growth
- Statewide cooperation to leverage support for evaluation of streambank erosion and quantification of its impact on phosphorus loads in the watershed
- Expansion of partnerships to reduce nutrients entering the FRIP study area, especially with the agricultural community in the most southern portion of the study area and with entities upstream in the Chain O’Lakes region of Illinois and Wisconsin
- Collaboration with other agencies and organizations on goals to eliminate impairments in the river due to pollutants besides nutrients and on goals to remove the river from the Illinois EPA list of impaired waters
Activities related to other action items conducted in 2025 are described below. The 2022 FRIP, an executive summary, and all appendices can be found at tinyurl.com/2022FRIPFolder.
U.S. Army Corps of Engineers Fox River Connectivity and Habitat Study
FRSG continues to work with U.S. Army Corps of Engineers, USACE, and the Illinois Department of Natural Resources, IDNR, to complete the Fox River Habitat and Connectivity Study, which was restarted in June 2022. This study is evaluating the efficacy and cost-effectiveness of fish passage and riverine function restoration methods at 10 low head, run-of-the-river dams on the Fox River from Algonquin to Montgomery. The FRSG has a Joint Funding Agreement with the IDNR to cover the local cost share needed to complete the study. In 2023, the Corps released the draft Project Implementation Report and Environmental Assessment (PIR/EA) for the Fox River Connectivity & Habitat Study in Kane and McHenry counties that recommended removal of nine of the 10 dams under study. The Algonquin dam was not recommended for removal. Modeling predicts dam removal is necessary to resolve river dissolved oxygen impairments. Without removing the dams, further phosphorus reductions by upgraded wastewater treatment plants would have little effect on total algae populations and would not eliminate the dissolved oxygen impairments within the dam impoundments, despite the high costs involved. In December 2025, the FRSG learned the Corps’ study paused while it underwent review by the Corps’ senior Administration personnel.
Forest Preserve District of Kane County’s Removal of Carpenter Dam
In October 2024, the Forest Preserve District of Kane County, in collaboration with IDNR, completed removal of one of the dams identified for removal in the Corp’s draft report. The Carpenter Dam was located within the District’s Fox River Shores Preserve on the Fox River in Carpentersville. Two projects documenting changes in water quality and mussel populations funded by the FRSG were completed in 2025 to document potential improvements to the Fox River from the Carpenter Dam removal.
Water Quality Hey and Associates, Hey, was contracted by FRSG to conduct water quality sampling at two locations to represent the sampling conducted in 2020 before the former Carpenter Dam was removed. Hey staff used water quality sondes to collect data at both locations from June 24to Oct. 30, 2025. Hey staff also collected discrete water samples 10 times during this period. On Sept. 8, 2025, two sediment oxygen demand (SOD) chambers equipped with a sonde were deployed in the former dam pool. SOD was calculated following the procedure outlined in the FRSG Quality Assurance Project Plan, QAPP. A final report documenting Hey’s work will be available on the FRSG website in 2026.
Freshwater Mussels
The Illinois Natural History Survey provided freshwater mussel population data in the Fox River to the Fox River Study Group in connection with the removal of the Carpenter dam. Survey sites were established at the Carpenter dam, at the Algonquin dam, and at a reference free-flowing, unimpounded reach near West Dundee. At each site, transects and timed searches were conducted in 2021 to establish a baseline of species richness and mussel density. In 2025, the INHS, with help from FRSG volunteers, conducted a preliminary post-demolition survey at the same locations. Across all surveys, mussel richness and abundance were lower at both dam sites as compared to the reference site at West Dundee. A final report will be available on the FRSG website in 2026.
Water Data Collection and Analysis
FRSG member groups collect and analyze samples using an all-volunteer and in-kind effort monthly since 2002. Sampling sites are at seven mainstem locations and seven tributary locations along an 80-mile stretch of the Fox River from McHenry to Yorkville. FRSG continues to fund the U.S. Geological Survey to collect continuous water quality data on the Fox River at the Stratton Dam, USGS Station #05549501, during the growing season. In 2025, USGS staff observed one potential blue-green algae bloom during their July 15 visit, but they were not able to collect a sample for toxin analysis.
The Illinois State Water Survey maintains the FoxDB environmental database, where all data for the Fox River watershed are compiled and made publicly available at ilrdss.sws.uiuc.edu/fox. Acquired water quality data from FRSG for the 2023-25 period are being compiled for the next database update.
Communications and Outreach
In 2025, FRSG conducted a number of outreach activities, both in-person and virtual. The FRSG helped plan and publicize the bistate Fox River Summit, held in March in Burlington, Wis., with both in-person and virtual attendance options. Videos of the presentations can be found at the 2025 Fox River Summit YouTube Channel. In the fall of 2025, the group held its annual meeting at Batavia City Hall with 70 attendees. The presentation slides can be found at foxriverstudygroup.org. In addition, the group has hosted two Lunch & Learn webinars. These included a session on Watershed Scale Changes in Nitrate and Total Phosphorus in the Lower & Upper Fox River Watersheds presented by U.S. Geological Survey staff and one on the USDA NRCS Regional Conservation Partnership Program presented by coordinators from Illinois and Wisconsin. The Lunch & Learn sessions typically attract 20 to 30 attendees. For more information, see foxriverstudygroup.org and the FRSG videos folder.